Regardless of the duration type of an activity, the following equation is always true: Remaining Units = Remaining Duration x Remaining Units/Time Preserve the Units, Duration, and Units/Time for existing assignments : Select this option for units, durations, and units/time to remain constant when additional resources are assigned to any activity.You can choose to preserve or recalculate units, duration, and units/time. Resource AssignmentsĪccessing the User Preferences within P6 Professional, and then selecting the Calculations tab, allows you to choose your Resource Assignment options.Ī dding or removing multiple resource assignments on activities options In this update we review how to set up Resource Assignments within the user preference calculations. While the majority of users leave Resource Assignments as the default setting, with a little piece of know-how you can use this area to greatly benefit your schedules.